Tunneling work at Woodberry/Limona Rds. and Lakewood Dr. Postponed
Tunneling work that was originally scheduled to begin soon at Woodberry/Limona roads and Lakewood Drive is being rescheduled.
As with any construction project of this scale, scheduling changes are a normal part of the process. The project team will send email alerts once the work is rescheduled and the necessary traffic permits have been issued. Variable message boards will be placed in the area two weeks before crews mobilize.
Meanwhile, tunneling work at Limona Road and the CSX Railroad crossing continues. Crews expect to begin open-trench excavation on Limona Road south of the railroad crossing in mid-April.
Tampa Bay Water’s contractor crews are performing this work as part of the South Hillsborough Pipeline construction. For more information on the pipeline, visit SouthHillsboroughPipeline.com.