Pipeline Schedule

Pipeline construction will begin in November:

  • Nov. 10: crews mobilize on Fishhawk Boulevard to install the pipe via horizontal directional drill under Fishhawk Creek 
  • Week of Nov. 16: night work in the Kings-Bloomingdale intersection to restripe the road for a new traffic pattern; crews mobilize at South Kings Avenue at Bloomingdale Avenue for microtunnel preparation; new traffic pattern begins  


More schedule details will be posted on this page as soon as they are available.

This graphic shows the schedule for the South Hillsborough Pipeline. Property acquisition runs from 2024 through fall 2026. Construction is scheduled for fall 2026 through the end of 2028. The pipeline is scheduled to be in service by the end of 2028 and final restoration will occur in the first half of 2029. Public outreach spans the entirety of the project schedule. The schedule is subject to change based on permitting and unforeseen conditions.