Pipeline Schedule
Following is the current schedule for the South Hillsborough Pipeline; all dates and locations are subject to change:
- Feb. 21 – crews mobilize on the south side of Fishhawk Boulevard for horizontal directional drill under Little Fishhawk Creek
- March 2 – crews mobilize at South Parsons Avenue/John Moore Road and Lumsden Road to begin work for a microtunnel under Lumsden; lane closures and detours on South Parsons Avenue and John Moore Road in effect
- March 10 – road closure begins at Woodberry/Limona roads for microtunnel work at Lakewood Drive
Work continues at:
- Fishhawk Boulevard near Fishhawk Creek
- Intersection of South Kings Avenue at Bloomingdale Avenue
- 7202 Alafia Ridge Road
- Limona Road and CSX railroad