Pipeline Schedule

The following schedule is subject to change and will be updated periodically.

  • Planning and preliminary design: began Sept. 2021 and completed July 2024
  • Property acquisition: summer 2024 – fall 2026
  • 60% design plans: summer 2024
  • 90% design plans: spring 2025
  • Permitting & final design: as early as fall 2025
  • Construction begins: as early as fall 2025
  • Construction complete: spring 2029
  • Pipeline in service: late 2028
  • Public outreach: entire project
  • Community meetings: early 2025 and summer/fall 2025